yrusOne ’ s newest 30 Megawatt Northern Virginia facility is completed in less than six months , shattering all known data center construction timelines
Global data center provider CyrusOne ( NASDAQ : CONE ) recently announced the recordsetting , six-month time period from ground breaking to completion of its newest 30 Megawatt facility on its Northern Virginia campus . Completed in less than six months , the project was delivered in the shortest known time to market interval for an enterprise scale data center of this size .
Driving this outstanding accomplishment was the company ’ s use of Massively
Modular ® engineering methods and advanced manufacturing supply chain techniques which enable the company to provide for the lowest costs and fastest time to market in the data center industry .
CyrusOne ’ s stated goal has been to improve its supply chain efficiency to the point whereby it can deliver a completed data center in the same timeframe that customers can order and receive the computing equipment that will reside in the data center . CyrusOne never wants its customer ’ s business objectives to be slowed down by the speed of their data center deployment . The record setting time it delivered the Northern Virginia facility proves CyrusOne can remove